LCA Tejas likely to get FOC by mid-2018, if not then definitely by the end of 2018: T.S Raju, HAL Chairman


LCA Tejas likely to get FOC by mid-2018, if not then definitely by the end of 2018: T.S Raju, HAL Chairman 

T Suvarna Raju, chairman of HAL in an interview with the Indian Express has said that HAL, ADA and Indian Air Force are jointly in process of achieving Final Operational Clearance (FOC) by mid of 2018, and if not then definitely by the end of 2018. 

HAL stands very strongly behind the LCA. We have established the production line capacity of eight aircrafts, the first five of them are already flying and have done more than 600 sorties. They are doing up. and we have kept things in place to produce eight and we are investing Rs 1,331 crore to increase the capacity to 16 deliverable a year. We have also used another concept of contracting the main components of the aircraft such as the front fuselage, centre fuselage, rear fuselage to L&T, WhAM, DTL. 

We have placed the orders. If these guys start giving me the required top-quality product, that adds to my deliverables. Now question comes, how much order I have. I have 20 IOC, of which I will provide 11 to IAF by the end of this financial year, and that would leave me with 4 fighters and 4 trainers, and trainers’ SOP we hope can be concluded so that the production run can be there.

As far as the FOC order is concerned, mid-2018 is when FOC is expected to come but we are asking the customer (IAF) to allow us to cut the material. Because if we start now, the aircraft will come after three years. By then, this AON of 83 LCA will be converted into a contract between the IAF and HAL. However, today the facilities are on and the rate at which jigs are created are available, and the purchase orders can be verified and checked.

The aircraft are flying and the operational capacity enhancement requires a thorough verification. It is a developmental work and we are planning to fly 60 sorties a month. Now between IAF, ADA and HAL, we are ensuring that these many sorties happen.

While the promises are for getting the FOC by mid-2018, we will definitely get it by December 2018. We should then be able to supply these 20 FOC by 2022. And then on to the next 83… If capacities are put on depending on the configuration clearance, the numbers can be rolled out. 

This is not like an automobile that today you give me a number and automatically I will give you the aircraft immediately. There is a lag, we require all the material to be procured and we need to make 10,000 odd components and put them together, and some components need to be bought from outside. 

The Indian Express 